Submittal vs Shop Drawing: What's the Difference?
Every shop drawing is a submittal, but not every submittal is a shop drawing. Here is how shop drawings differ from product data, samples and other submittals, and why the difference matters for review.
· 3 min read
The terms submittal and shop drawing are often used as if they mean the same thing. They do not. A submittal is any document or item the contractor provides to the design team to show how it will meet the contract documents. A shop drawing is one type of submittal: a drawing prepared by the contractor, a subcontractor or a fabricator that shows exactly how a particular part of the work will be made and installed.
Every shop drawing is a submittal, but most projects also require many submittals that are not shop drawings. Knowing the difference helps teams build a complete submittal log and route each item to the right reviewer.
What a Submittal Is
A submittal is the contractor's demonstration, before work is fabricated or installed, that what it intends to build conforms to the drawings and specifications. Each specification section lists the submittals it requires, and Division 01 sets out how they are prepared, numbered and reviewed. What Is a Construction Submittal? explains the whole process.
What a Shop Drawing Is
A shop drawing translates the design drawings into the detail needed to fabricate and install a specific component. The architect's drawings show what is wanted: a stair, a curtain wall, a run of ductwork. The shop drawing shows how it will be built: member sizes, dimensions, connections, anchors, materials, tolerances and how it meets adjacent work.
Shop drawings are common for structural steel, miscellaneous metals, precast concrete, curtain wall and windows, millwork, ductwork, sprinkler layouts, elevators and other fabricated or custom systems. Where the specification delegates part of the design to the contractor's engineer, such as steel connections or precast panels, the shop drawings may need to be sealed by a professional engineer licensed in the province or state.
Other Types of Submittals
Alongside shop drawings, a typical project requires product data, which is the manufacturer's literature showing that a standard product meets the specification; samples of finishes, colours and materials; mock-ups for assemblies such as a section of masonry or curtain wall; test reports and certificates; design data and calculations; and closeout submittals such as operation and maintenance manuals, warranties and as-built records.
Product data and shop drawings are often confused. The difference is that product data describes a standard manufactured product, while a shop drawing describes something made or arranged for this specific project.
Why the Difference Matters
Shop drawings usually take longer to prepare and to review than product data, because they involve coordination with other trades and with the structure. They often sit on the critical path for long-lead items: fabrication cannot start until the shop drawings come back, and a curtain wall or a steel package may then take months to fabricate.
That affects planning. Shop drawings for long-lead items need to be scheduled early, with time allowed for at least one resubmission. How to Build a Construction Submittal Schedule shows how to work those dates backwards from the installation date.
How Shop Drawings Are Reviewed
The consultant reviews shop drawings for general conformance with the design intent and the contract documents. The review does not relieve the contractor of responsibility for dimensions, quantities, fabrication methods, coordination between trades or the means and methods of construction. Most review stamps say so explicitly.
Typical review actions are 'reviewed', 'reviewed as noted', 'revise and resubmit' and 'rejected'. Work can usually proceed on the first two, incorporating any notes; the other two require a new submission.
Tracking Both in One Log
Shop drawings, product data, samples and closeout documents should all live in one submittal log, organized by specification section, with the type of each submittal recorded. That makes it easy to see which shop drawings are still outstanding for long-lead items, and to filter the log for the reviewer of each type.
Submittal tracking software keeps that log current as packages move between the contractor and the consultant. Our free submittal log template is a good starting point for smaller projects.