How to Build a Construction Submittal Schedule from Lead Times

Late submittals are one of the most common causes of procurement delays. Here is how to work each submittal date backwards from the installation date, with an example and the allowances most teams forget.

· 3 min read

A submittal schedule sets the date each submittal must be sent so that the material it covers arrives on site in time to be installed. It is built backwards: from the date the work needs to start, through delivery, fabrication and review, to the date the contractor has to submit.

Without one, submittals tend to be prepared in the order that is convenient rather than the order that matters, and long-lead items are discovered late. With one, the project team knows months in advance which packages are on the critical path.

Start with the Submittal Register

List every required submittal from the specification, section by section, before scheduling anything. Each specification section names its own submittals in Part 1, and Division 01 adds general requirements. A submittal log by spec section is the foundation; our AI submittal list generator can build a first draft of the register from the specification divisions on your project.

For each submittal, note the type (shop drawing, product data, sample and so on), the subcontractor responsible and the schedule activity it supports.

The Backward Calculation

For each submittal, start with the date the related work must start on site, then subtract each step in turn: delivery to site; fabrication or manufacturing time; the consultant's review period; a further review period plus revision time, to allow for one resubmission; and the time the subcontractor or supplier needs to prepare the submittal.

The result is the date the submittal must be sent. Add a 'required by' date for the subcontractor a week or two before that, so the general contractor has time to review it before forwarding.

A Worked Example

Take a curtain wall package where installation must start in week 30 of the project. The numbers below are illustrative; use the lead times your suppliers actually quote.

Fabrication and delivery take 16 weeks, so the shop drawings must come back reviewed by week 14. The specification gives the consultant 2 weeks to review. Allow one resubmission: another 2 weeks of review plus 1 week for the contractor to revise, so the first submission must reach the consultant by week 9. The curtain wall subcontractor needs 3 weeks to prepare the shop drawings and calculations, so they must start by week 6, which means the subcontract has to be awarded before then.

A package that looks months away on the construction schedule turns out to need action in the first weeks of the project. That is the point of the exercise.

Allowances Teams Often Forget

Teams commonly underestimate several things: the general contractor's own review time before forwarding; consultant review periods that run in parallel across disciplines, such as architectural and structural review of the same package; resubmissions, which are common for complex shop drawings; holidays and supplier shutdowns; and samples or mock-ups that must be approved before shop drawings can be finalized.

Lead times also change. Confirm them with suppliers when the schedule is built, and again when the submittal is sent.

Linking Submittals to the Schedule

Each submittal should be linked to the schedule activity it supports. When the construction schedule moves, the submittal dates move with it, and when a submittal slips, the affected activity is visible. Reviewing the submittals due in the next three to six weeks at each coordination meeting keeps the critical ones in front of everyone; a three-week look-ahead is a natural place to do that.

Keeping It Current

A submittal schedule is only useful if it reflects reality. Record the date each submittal is actually sent and returned, its review action, and any resubmission. Track the median review time by consultant; if reviews are taking longer than the specification allows, raise it early with real numbers rather than at the point a delay is unavoidable.

Submittal tracking software records those dates as packages move, shows what is overdue, and in PlanSpan measures turnaround and prepares reminders before due dates for a project manager to approve. A missed submittal date is far easier to recover from in week 6 than in week 28.