How to Write a Clear Construction RFI (With Examples)

Most slow RFI answers start with a vague question. Here is how to write an RFI the design team can answer in one pass: one question, exact references, a proposed answer and a real due date.

· 4 min read

The fastest way to get an RFI answered is to write it so that the reviewer does not need to ask anything back. A vague RFI generates a clarification request, a phone call or a second RFI, and each of those adds days while the work it affects waits.

Writing a clear RFI takes a few extra minutes. Those minutes come back many times over in a faster answer, and in a project record that still makes sense when someone reads it a year later.

Check the Documents First

Before writing anything, confirm that the answer is not already in the documents. Check the current revision of the drawings, the specification section, any addenda issued during tender, and previous RFI responses on the same topic. A surprising share of RFIs are answered by a later revision or an earlier response that the person asking had not seen.

If the documents do answer the question but the answer is unclear or inconvenient, say that in the RFI. Quote what the documents say and explain why it needs confirmation. That is a better RFI than one that pretends the information is missing.

Ask One Question

Each RFI should contain one question. If a field walk turns up three problems on the same floor, write three RFIs. They may go to different consultants, they will be answered at different speeds, and each answer may affect a different part of the work. An RFI that bundles them stays open until the last part is resolved, and the log no longer shows which issue is actually holding up work.

Write the question so that it can be answered with a short, definite response. 'Please confirm whether the 1,000 mm spacing in the specification governs over the 1,200 mm spacing shown in detail 4' can be answered in one line. 'Please advise on guardrail requirements' cannot.

Give Exact References

Name the drawing sheet, its revision and the detail or grid lines; the specification section and paragraph; and any related RFI or submittal by number. The reviewer should be able to open the right page without searching.

A marked-up drawing or a photo usually saves more time than another paragraph of description. Circle the conflict, add dimensions where they matter, and attach the image to the RFI rather than linking to a shared folder that may change.

Propose an Answer

Where the contractor has a sensible solution, include it. A proposed solution turns the reviewer's task from designing an answer into confirming or adjusting one, which is usually much faster. It also shows the design team that the field has thought about constructability.

Keep the proposal factual. If it changes cost or time, say so. A proposed solution is not an acceptance of extra cost, and it is not a substitution request; substitutions follow their own procedure in the specification.

State the Impact and a Real Due Date

Say whether the answer is likely to affect cost or schedule, and give the date a response is needed, with the reason: 'Fabrication starts on March 4; a response is needed by February 25 to hold that date.' A reason makes the due date credible, and it gives the project manager something concrete to point to when following up.

Avoid marking every RFI urgent. When everything is urgent, nothing is, and reviewers start to discount the dates. Check the contract and Division 01 for any required response period and use it.

Before and After: An Example

Before: 'Mechanical and structural don't line up at Level 3. Please advise ASAP.'

After: 'Subject: Duct conflict with beam B3-14 at gridline C/4, Level 3. References: M-301 revision 2; S-301 revision 4. Question: The 600 x 300 mm supply duct shown on M-301 runs with its top at 3,250 mm, which conflicts with beam B3-14, whose underside is at 3,100 mm on S-301. Can the duct drop below the beam, with its top at 3,050 mm and its underside at 2,750 mm, or should it run around the beam to the east as shown in the attached sketch? Proposed solution: drop the duct; the 2,600 mm ceiling height is maintained with 150 mm to spare. Impact: no cost impact for the drop; ductwork installation on Level 3 starts March 10, so a response is needed by March 3.'

The second version can be answered in one reply. The first will almost certainly come back with questions.

Templates and Tools That Help

A consistent format makes good RFIs the default. Our free construction RFI template includes every field described above.

In PlanSpan, a field issue from a daily report, a photo or a voice note can be turned into a structured RFI draft with the drawing and specification references filled in. The person raising it checks the draft before it is sent, and the RFI is numbered and tracked in the project's RFI log from that point on.

Your next RFI, already drafted

See it on your own project.

PlanSpan prepares cited RFI responses and first-pass submittal reviews from your own drawings and specifications. Start free with one project.