Construction Submittal Log Template

Free to download and use, with guidance on how to fill it in.

Download this template

Free to use. No email required.

Download Free Template

What it is

A submittal log is the master tracking document for all required submittals on a construction project. It lists every product data sheet, shop drawing, sample, calculation, and certification that must be submitted for design team review and approval before materials are fabricated, procured, or installed. A complete submittal log, started at project kick-off and maintained throughout construction, is one of the most effective tools for keeping a project's procurement schedule on track and preventing closeout surprises.

When to use it

Develop your submittal log during pre-construction, before any submittals are prepared. The log should be reviewed and agreed with the design team at the pre-construction meeting. Use it throughout construction to monitor which submittals have been prepared, which are under review, which have been approved, and which require resubmission. Review the log at every project meeting and use it to drive the subcontractor submittal preparation schedule.

How to complete it

  1. 1

    Review every specification section for submittal requirements

    Read the submittal paragraph of every applicable specification section. The specification will list exactly which submittals are required — product data, shop drawings, samples, calculations, certifications, and any project-specific documentation. Do not assume you know what is required; read the specification.

  2. 2

    Assign a submittal number to each item

    Number submittals by specification section and sequential item number — for example, 03-01 for the first submittal under Division 03, 03-02 for the second, and so on. This system links every submittal directly to its specification section.

  3. 3

    Determine required approval dates from your schedule

    For each submittal, work backward from the required-on-site date through the manufacturing lead time and contractual review period to determine the date by which the submittal must be approved. Then calculate the date by which the submittal must be transmitted to allow for the review period.

  4. 4

    Assign submittal responsibility to subcontractors

    For each submittal, identify which subcontractor is responsible for preparing and submitting it. Include the subcontractor's name and PM contact in the log.

  5. 5

    Track status and review actions

    Record the date each submittal is transmitted, the date it is returned, and the review action received: Approved, Approved as Noted, Revise and Resubmit, or Rejected. If a resubmittal is required, track the resubmittal date and action separately.

  6. 6

    Flag items approaching critical dates

    Highlight any submittal whose required transmission date is within two weeks and which has not yet been submitted. These items need immediate follow-up with the responsible subcontractor.

Common mistakes to avoid

Building the log from memory instead of the specification

The most common cause of missing submittals at closeout is a log that was built from the contractor's memory of what submittals are typically required, rather than from a systematic review of the actual specification sections. Read every section.

Not connecting the log to the procurement schedule

A submittal log without required approval dates is a filing system, not a management tool. The log becomes useful when every item has a date that can be compared against the calendar.

Approving submittals before the GC review stamp

Most contracts require the general contractor to review and stamp every submittal before it is transmitted to the design team. Submitting unstamped shop drawings or product data sends the message that the GC has not fulfilled its own review obligation — and experienced reviewers will return them immediately.

Closing the log at approval without tracking distribution

An approved submittal that is not distributed to the installing subcontractor and superintendent is useless in the field. The log should include a distribution column to record when approved submittals were sent to the people who need them.

How PlanSpan automates this workflow

PlanSpan's submittal tracking gives every project a live submittal log organized by specification section, with status tracking through every stage from Draft to Approved. Submittals are numbered automatically, review actions are recorded with timestamps, and the full resubmittal history is retained for every item. AI can compare submitted product data against your uploaded project specifications to flag deviations before the package is transmitted to the design team — catching problems in minutes rather than discovering them after a rejection.

See how PlanSpan tracks submittals →

Download this template

Free to use. No email required.

Download Free Template
Back to all templates