Construction Submittal Review Checklist: What to Check Before You Submit or Approve

A practical checklist for reviewing construction submittals, for the contractor before sending a package and for the consultant before returning it, so fewer submittals come back for resubmission.

· 3 min read

Most submittal resubmissions are avoidable. The product did not match the specification, a required certificate was missing, or the shop drawing showed a dimension that conflicts with the architectural drawings. Each of those could have been caught by a careful review before the package left the contractor's office.

This checklist covers both sides of the process: what the contractor should check before submitting, and what the consultant typically checks before returning a submittal. It is a starting point; the specification for each section always governs.

Before You Start: Know the Requirements

Open the specification section the submittal belongs to and read its submittal requirements, usually in Part 1. Note exactly what is required: product data, shop drawings, samples, test reports, certificates, warranties or delegated-design calculations. Then read the general submittal procedures in Division 01, usually section 01 33 00, for formatting, numbering, transmittal and review-period requirements.

Building the list of required submittals from the specification at the start of the project, rather than package by package, avoids discovering a requirement late. A submittal log by spec section makes that list visible.

Contractor Checklist: Before You Submit

Check that the submittal is for the correct specification section and is numbered according to the project's system. Confirm that the product named is the one specified, or an approved equal, and that substitutions have followed the specified procedure rather than being slipped into a submittal.

Check each specified performance requirement against the product data: ratings, sizes, finishes, capacities, fire ratings and code compliance. Mark the exact model, size and options on any manufacturer's data sheet that covers several products; generic catalogue pages are one of the most common reasons for rejection.

Check shop drawings against the current architectural and structural drawings for dimensions, elevations, connections and interfaces with adjacent work. Confirm that every required document is included, such as certificates, test reports and engineer's seals for delegated design. Finally, review and stamp the submittal as the contract requires before it is sent. Forwarding a subcontractor's package without review defeats the purpose of the contractor's stamp.

Consultant Checklist: Before You Return It

The consultant reviews for general conformance with the design intent and the contract documents. Typical checks include whether the submittal addresses the right specification section and paragraph requirements; whether the product meets the specified performance criteria; whether any deviations from the specification are clearly identified by the contractor; whether shop drawings coordinate with other disciplines; and whether all required documents are present.

Review comments should be specific enough to act on. 'Provide fire rating documentation per 07 84 00, 2.2.A' leads to a correct resubmission. 'Incomplete' leads to another round.

Common Gaps the Checklist Catches

The same issues come up again and again: a substitution submitted as if it were the specified product; missing project-specific information on standard data sheets; shop drawings prepared from superseded drawings; missing certificates or test reports; and resubmittals that address some review comments but not all of them. Common Reasons Submittals Are Rejected looks at each of these in detail.

Resubmittals

When a submittal comes back marked 'revise and resubmit', respond to every comment, in writing, and cloud or otherwise mark the changes on the revised documents. Keep the same submittal number with a revision suffix so the history stays together. A resubmittal that only addresses some comments is likely to come back again, and every extra cycle eats into the time before fabrication.

Using AI for the First Pass

Much of this checklist is a comparison between the submittal documents and the specification, which is exactly the kind of work AI can do quickly. PlanSpan's submittal compliance check compares a package against the specification before it is sent, flagging deviations and missing documents. On the consultant side, an AI first-pass review prepares draft comments for the reviewer to check.

Neither replaces the professional review. They make sure the reviewer starts from a list of likely issues rather than a blank page, and every comment is approved by a person before it goes out.