Construction Daily Report Template

Free to download and use, with guidance on how to fill it in.

Download this template

Free to use. No email required.

Download Free Template

What it is

A construction daily report is a written record of site activity logged at the end of each working day. It documents who was on site, what equipment was used, what work was performed, what the weather conditions were, and any notable events — inspections, visitors, safety incidents, delays, or issues requiring follow-up. Daily reports are the primary source of contemporaneous project documentation and are routinely used in claims, disputes, and insurance matters to establish what happened on site and when.

When to use it

Complete a daily report every working day the project is active, even if very little work was performed. A short report documenting that only one trade was on site due to weather is more valuable than a gap in the record. Daily reports should be completed at the end of the working day while the information is current — not reconstructed the following morning or summarized weekly. Every report should be dated, signed by the superintendent, and filed in the project record.

How to complete it

  1. 1

    Date and project information

    Record the project name, project number, contract number, date, day of the week, and the name and title of the person completing the report. Never complete a report without a date — an undated daily report is not useful as a contemporaneous record.

  2. 2

    Weather conditions

    Record the temperature at the start and end of the working day, precipitation (type and approximate amount if any), wind conditions, and any weather event that affected productivity or required work to be stopped. Weather documentation is important for any future claim related to weather-related delays.

  3. 3

    Labour on site

    List each trade or subcontractor present on site, the company name, the foreman or supervisor, the number of workers by classification (journeyman, apprentice, labourer), and the hours worked. Total all labour hours at the bottom of the section.

  4. 4

    Equipment on site

    List each piece of major equipment on site — cranes, excavators, concrete pumps, man lifts, compactors — with the equipment type, operator, and hours of operation. Note any equipment that was idle and the reason.

  5. 5

    Work performed

    Describe the work performed by each trade in sufficient detail that someone reading the report six months later would understand what was accomplished. Include locations, quantities where relevant, and any notable milestones — first pour complete, structural steel topped out, roofing membrane installed on Level 3.

  6. 6

    Visitors, inspections, and notable events

    Record any site visitors (owner, architect, inspector, engineer), any inspections performed and their results, any safety incidents or near misses, any deliveries of major materials, and any issues that may affect the schedule or cost.

  7. 7

    Delays and issues

    Document any delays that occurred during the day — weather, material delivery failure, equipment breakdown, trade conflict, or any other event that reduced productivity — and their estimated impact on the schedule. This documentation supports any future claim for an extension of time.

Common mistakes to avoid

Vague descriptions of work performed

A daily report that says 'concrete work' or 'mechanical rough-in continued' is not useful documentation. Describe specifically what was done, where, and how much — 'poured suspended slab on Level 4, grid A through E, approximately 180 cubic metres.'

Missing labour or equipment counts

Labour and equipment records are used to calculate productivity rates, verify subcontractor invoices, and support delay claims. Incomplete counts reduce the value of the report significantly.

Not documenting delays the same day they occur

A delay that is documented in the daily report on the day it occurred is a contemporaneous record. A delay that is described in a letter three weeks later is a reconstruction. Courts and arbitrators weight contemporaneous records significantly more heavily.

Reports completed days after the fact

A daily report dated Tuesday that was actually written the following Monday is not a daily report — it is a weekly summary written from memory. If a gap in the record exists, note it explicitly rather than backdating.

No photos

Daily report photos documenting site conditions, progress milestones, and notable events are among the most valuable pieces of project documentation. A written description of a condition is far less compelling than a dated photograph.

How PlanSpan automates this workflow

PlanSpan's daily reporting tools let field teams log labour by trade, equipment hours, weather, work performed, and photos from any phone or tablet — with structured fields that match this template exactly. Voice logging lets a superintendent dictate the entire report while walking the site; AI transcribes and fills in the fields automatically. PlanSpan then uses your daily logs to generate AI weekly summaries, monthly progress reports, and invoice work descriptions — turning your daily documentation into ready-to-send client reports with no additional writing.

See how PlanSpan handles daily reports →

Download this template

Free to use. No email required.

Download Free Template